Road construction season is almost underway. This list will be updated with road closures and changes to traffic patterns as projects progress.
Anticipated Project Start Date
| Road(s) Affected
| Details | Anticipated Project Completion Date |
---|
August 18 | Twp. Rd. 641 between Rge. Rd. 432A and Rge. Rd. 434 | Rip and Relay project. Some short delays during daylight hours. Open to traffic. | end of August (weather dependent) |
August 18 | Twp. Rd. 624 between Hwy. 881 and Rge. Rd. 485 | Shoulder pulls being done. Open to traffic. May have some delays during daylight hours. | end of August (weather dependent) |
August 25 | 48 Ave. in Ardmore | Storm sewer installation. Traffic impact will be minimal. | mid-October 2021 |
September 20 | Rge. Rd. 485, south of Hwy. 28 | Bridge Replacement. The bridge will be closed for four to six weeks. Please follow all signs. Traffic detours are via Rge. Rd. 490 or Rge. Rd. 484. | mid-October to end of November 2021 |
September 17 | Rge. Rd. 442A | Rip and Relay. Some traffic delays may occur |
|
September 17 | Rge. Rd. 463, north of Twp. Rd. 620 | Road being rebuilt. Traffic delays may occur. |
|